SunTrust Bank


5,000 SF interior build-out

Complete gut/demo of existing tenant space located in the SCI Tower downtown

New offices, new sprinkler systems, MEP systems, interior storefront, new MDF room

 

Construction timeframe: 90 days (completed within 75 days)

Architect: DSI Architecture, Inc – Eddie Muse

 

Design Features:

  • Advanced security and communication systems installed
  • Project was intensely coordinated with SunTrust personnel, staffing, and owner subcontractors (comms, security, furniture) because all were based out of town.
  • The owner subcontractors had to be scheduled way in advanced, so the schedule had to be updated and held precisely to the day(s) that listed specific owner subcontractor tasks
  • Project was complete 2 weeks early
  • MDF room had to be completed ahead of the rest of the schedule, for the owner IT subcontractor to order and install comms circuits
  • Multiple change orders were involved in the project, and it was still completed early

Additional Details:

  • All offices had storefront door systems
  • Wall paper/graphic designs installed to match corporate standards
  • The space’s waiting room ceiling was a unique design the consists of a drop down cloud ACT ceiling off of a hard ceiling with an owner supplied chandelier install in the cloud