Project Details

  
Pyramid, Inc.


  • 2,500 SF addition added to existing building for art classrooms, bathrooms, and 200 sqft addition added to front of building
  • New Construction of 2500 sqft addition onto existing that included art classrooms, bathrooms, and mechanical room.
  • Re-route and replace entire civil system for storm water drainage, and for new utilities in new additions.
  • Renovations to the existing of the building that included converting a car port located at the front entrance of the building into an art gallery. Renovation to existing space to create a reception area, two offices, and a copy/file room.

Construction timeframe: 180 days

Architect: Sam Marshall Architects – Mike Marshall

 

Design Features

  • Pyramid, Inc. remained open and operating throughout construction
  • Pyramid, Inc is a school for adults with “special needs”, so the precautionary measures for safety, and the sensitivity for noise and construction interference was extremely high. We were able to complete the project with no incidents, and no major issues for Pyramid, Inc. with their operations.
  • New civil work and drainage system improved the conditions of the courtyard located in the center of the building, and Pyramid no longer has any problems with water intrusion/minor flooding inside their building during/after rain storms.
  • Wood framed construction; between new addition and reno to existing, added 4 new classrooms
  • Project consisted of over 20 change orders/scope changes to the contract